The City entered into an agreement with contractor Continental Construction Company for $951,667.40 on November 25, 2019 for the construction of two bike lanes, new watermain line and roadway improvement on NE 183rd Street between NE 11th Avenue and NE 19th Avenue. The project is funded jointly by the FDOT through the Local Agency Program (LAP), Citizens Independent Transportation Trust (CITT), the Water Infrastructure and Innovation Act (WIFIA) and the City of North Miami Beach. This project was completed in December 2021. During the construction, additional work was approved and performed to avoid further delay in the project completion. A request is now being made to approve the cost of this work.
To finalize payments to the Contractor and close out the project, a final determination of all works and associated costs was completed, which is in the amount of $1,146,863.74. This item is for the ratification of the change order in the amount of $93,229.19 for concrete and asphalt quantity overrun, electrical installations for irrigation, and works associated with water connections.