Item Coversheet
 Quasi-Judicial Legislation
10.2.


City of North Miami Beach
17011 NE 19 Avenue
North Miami Beach, Fl 33162
305-947-7581
www.citynmb.com

MEMORANDUM



 

TO:Mayor and City Commission
FROM: Esmond K. Scott, City Manager
VIA: 

Justin Proffitt, AICP, Director of Community Development

Sharon Cino, Planning and Zoning Manager

Mario Duron, AICP, Associate Planner 

DATE:September  24, 2020



 RE: Ordinance No. 2020-08 (First Reading) Approving Master Development Agreement and Conceptual Master Plan Request by Dezer Intracoastal Mall, LLC (Justin Proffitt, AICP, Director of Community Development)


Description
 
BACKGROUND ANALYSIS:


 

APPLICATION SUMMARY: The Applicant/Property Owner, Dezer Intracoastal Mall, LLC, requests approval of a Development Agreement incorporating a Conceptual Master Plan (CMP) to construct a phased project called the Intracoastal Mall Redevelopment.

 

The CMP envisions 2,000 multifamily residential units, up to 375,000 square feet of commercial/retail space, 200,000 square feet of office space, and a 250-key hotel.

 

 This project was reviewed by city staff at the TRAD, Technical Review of Applications for Development Committee on:

1.      TRAD (Aug. 30,2019)

2.      TRAD II (March 26, 2020)

3.      TRAD Sign-off for PZB (May 15, 2020)

 

 The item was presented at the Planning and Zoning Board (PZB) meeting held on July 13th, 2020, and was recommended for APPROVAL by a vote of 4-3.

 

 

 RECOMMENDATION:


 

PLANNING AND ZONING BOARD RECOMMENDATION:

The Planning and Zoning Board met on July 13, 2020 and recommended APPROVAL of the Development Agreement with the associated CMP, by a vote of 4 to 3, with the following recommendations to the City Commission (these recommendations have been agreed to by the developer and are included in the Development Agreement and the conditions below):

 

  • Public Art Condition: The Developer shall provide artwork with a total aggregate value of at least One Hundred Thousand Dollars ($100,000). The artwork, which may consist of murals, graphics, interactive fountains, streetscape designs, or similar pieces of artwork to be provided by Developer shall consist of a minimum of two (2) pieces of art to be installed on-site or on adjacent rights of way or public property and shall be of a quality and design reasonably acceptable to the City Manager, or designee, with a recommendation by the Community Development Director .
  • Jobs Condition: The Developer shall work with the City of North Miami Beach Human Resources Department to advertise employment opportunities and use good faith efforts to promote the hiring of City residents to fill employment positions within the development during all phases of construction and development. 
  • NE 35th Avenue Improvements Condition: The developer shall design the proposed NE 35th Avenue streetscape and infrastructure improvements to be consistent with the City’s designs in the NE 35th Avenue Roadway Enhancements Project and the Mixed Use District zoning regulations, less any adjustments required by FDOT or Miami-Dade County. 

 

 

COMMUNITY DEVELOPMENT DEPARTMENT RECOMMENDATION:

The Community Development Department recommends the City Commission APPROVE the Development Agreement and the associated Conceptual Master Plan with the conditions of approval in the staff report.

 FISCAL/ BUDGETARY IMPACT:
 

Summary of Public Benefits

 

REQUIRED BY CODE PER SEC. 24-58.7(O) DEVELOPMENT APPROVAL CONDITIONS

ESTIMATED COST

1) Public Infrastructure and Streetscape Assessment and Funds

2) Fire Rescue Station.

3) Police Substation.

4) Six (6) acres of publicly accessible open space and waterfront promenade

5) Multiple access points, including to and from SR 826 and traffic mitigation on NE 35th Avenue.

6) Streetscape improvements

1) $900,000

2) $1,8000,000

3) $750,000

4) Included in overall Development Cost.

5) $7, 500,000

6) Included in overall Development Cost.

ADDITIONAL CONTRIBUTIONS

ESTIMATED COST

1) Relocation and Improvement of Existing Lift Station

2) Extension of Existing Gas Line

3) On-site Community Center

4) Dredging Canal into the Site for Additional Public Open Space

5) Premium Transit Shelters with Digital Displays, Wi-Fi Access

6) Public Art

1) $1,000,000

2) $800,000

3) Included in overall Development Cost.

4) $35,000,000

5) Included in overall Development Cost.

6) $100,000

Table 5. Summary of public benefits required by code and additional contributions by developer. Estimated costs based on Fiscal Study and findings by the Applicant.

 

The Developer provided a Fiscal Impact Study (FIS) prepared in connection to the review of the proposed Intracoastal Mall Master Plan. The FIS was prepared by Integra Realty Resources, dated March 25, 2020. The City’s Economist, Lambert Advisory peer-reviewed the study and agree with the study’s findings. The following is a summary of findings based on the scope of work in the Conceptual Master Plan: 

 

Public Infrastructure Benefits*

  •  Relocation and Improvement of Existing Lift Station (estimated cost $1,000,000)
  •  Extension of the Existing Gas Line along NE 35 Ave from 3405 NE 163 ST ($800,000)
  • Roadway Improvement to 35th AVE and other Off-Site Roadway Improvements (estimated cost $7,500,000)
  •  Public Infrastructure and Streetscape Assessment totaling $900,000 ($450 per residential unit) 

 

Public Facilities*

  •  Relocate, Enlarge and Improve Existing Fire Station (estimated cost $1,800,000)
  • 1500 SF Police Substation (estimated cost $750,000)
  • Dredging Canal into the Site for additional Publicly Accessible Open Space (estimated cost $35,000,000)

 

Job Creation

  •  Existing Conditions: 633 retail/office job
  • During Construction: 11,800 temporary jobs
  • After Redevelopment: 2,700 permanent jobs

*Capital improvements are creditable toward applicable impact fees.

 

The FIS estimated the construction of the project will generate $7.2 million in Impact Fees for the City, and upon completion and stabilization, an increase of the Ad Valorem Taxes to $11 million per year. Based on the findings in the FIS, the estimated Developer Contributions to the project total over $54,850,000 (Integra Realty Resources, Fiscal Impact Study, dated March 25th, 2020).




ATTACHMENTS:
Description
Ordinance Approving Intracoastal Master Development Agreement
Intracoastal Mall Development Agreement - DRAFT
City Staff Report
Intracoastal Mall Comprehensive Plan Policies in Staff Report
Article VII Oleta River Overlay District Ordinance
Intracoastal Mall Application
Intracoastal Mall Fiscal Impact Study
City's Economist Fiscal Imapact Review
Intracoastal Mall Hurricane Analysis
Intracoastal Mall updated July 2020 Traffic Analysis
City's Traffic Engineer Traffic Study Response
FDOT AMRC Comments from 9-10-20 Mtg Applicant Response
FDOT AMRC Meeting 9-10-20 Comment Summary
July Planning and Zoning Board Meeting Minutes
Intracoastal Mall Conceptual Master Plan
Intracoastal Mall Landscape Plans
Intracoastal Mall Civil Plans
Intracoastal Mall Plat_Survey
Intracoastal Mall Survey
Intracoastal Mall TRAD Responses
Public Comments Received up to 7/13
Public Comments Received 7/13 to 9/24/2020
Development Agreement Term Sheet Summary